Schedule

Overall Project Progress
41%

The County Road 43 Widening Project work began in March of 2024, and is is anticipated to be completed in early 2027. Much work has been completed to date, including:

  • Installation of storm sewers and new asphalt being laid
  • Substructure work on the bridge, placing concrete as well as abutments (structure footings) on both sides of the bridge
  • Underground infrastructure along the south side of CR43 between Anniversary Way and King Street towards the river

Take a look at the progress of major milestones anticipated to be completed in the upcoming years:

Project Progress

Installation of new underground utilities
60%
Bridge Progress
45%
Construction of two new lanes on North of CR43
40%
Removal and reinstatement of existing entryways
35%
Installation of Multi Use Pathways
25%

Check back here for updates on project progress!