Project Details
Q: What is the projected total cost of the project?
A: More than $40 million.
Q: What portion of the project cost is covered by the Municipality of North Grenville?
A: Roughly $10 million.
Q: Who will be doing most of the work?
A: The majority of work will be completed by the Contractor R.W. Tomlinson Ltd.
Q: What is the total duration of the contracted road works?
A: The project began in March of 2024 and is anticipated to be completed in late 2026, we are expecting the duration to last roughly 2.5 years.
Q: How far past County Road 44 is the 4-lane project going west?
A: Approximately 200 metres, County Road 43 will remain 2 lanes west of 43/44 roundabout.
Q: How many roundabouts will there be, and will there be flashing pedestrian-controlled lights?
A: There will be six roundabouts at the completion of the project (this includes Colonnade and County Road 19). The roundabouts will have flashing pedestrian-controlled lights installed.
Q: Will there be two expanded roundabouts? Where will the four new roundabouts be located?
A: Yes, there will be two expanded roundabouts. The four new roundabouts will be located at Stinson/Kemptville Retirement Living, Anniversary Way, Shoppers Plaza, intersection of County Road 43 and County Road 44.
Q: Will there still be a roundabout at Somerville and County Road 43?
A: Yes, that is outside of this project but is still in the plans to be implemented.
Q: Is the multi-use pathway separated from the road, and if so, how?
A: There is 1.5 metres between the curb and the pathway to accommodate snow plowing in the winter months.
Q: When will construction of the new bridge begin?
A: Construction of the new bridge is expected to begin in July of 2024, beginning with the development of the footings. Pedestrians can expect to see more significant changes to the bridge in 2025.
Q: Will the bridge crossing be demolished and rebuilt, or will it undergo repairs alongside new construction? Will there be two bridges or one with four lanes?
A: There will be one 4 lane bridge. We are constructing two lanes on the south side of the bridge in 2024, then moving traffic to them, then constructing the other two lanes and joining them.
Q: Will the new bridge maintain the same clearance?
A: Yes, it will have the same bridge clearance as the current bridge.
Traffic Impacts
Q: What are the expected traffic impacts?
A: Expect small traffic impacts and disruptions such as short term single lane closures and short term entryway closures. We will provide as much advance notification as possible based on operations that have traffic impacts.
Q: How far north will the disruption be from the intersection of County Road 43 and County Road 44?
A: The work will continue approximately 200 metres North.
Q: Are there temporary traffic management measures planned for Wellington/Bridge/Van Buren streets due to anticipated increased traffic?
A: None are planned at this time, but we will be monitoring for impact and the Municipality is prepared to respond as needed. There will be no signed detours and we are not planning to close County Road 43 to traffic. If for any reason there is any temporary traffic disturbances, the public will be notified and signage and alternate routes will be provided to the public ahead of time, whenever possible.
Q: Are there designated alternate routes, and what plans are in place for traffic mitigation on Wellington Street?
A: No alternate routes were initially proposed as most locals find their own way. That being said, we will be monitoring for any issues that arise and we are prepared to respond quickly as needed. Additionally, North Grenville Council approved traffic calming measures for Wellington this year. These will be implemented in 2024, though they will not be in place at the start of construction on the County Road 43 project.
Q: What will be the speed limit on the new boulevard?
A: The speed limit will be 50km/hr for the entirety of the project area.
Q: Will the new multi-use pathway on both sides of the boulevard be illuminated?
A: Yes, there will be adequate lighting on both sides of the boulevard for pedestrians to safely travel at night.
Q: County Road 43 experiences significant truck traffic. Are the roundabouts designed to accommodate this?
A: The roundabouts are bigger than what is currently in place, and in some cases larger trucks will use both lanes to pass through. The roundabouts are designed to accommodate trucks, agricultural vehicles, etc.
Hydro
Q: What are new hydro poles being installed?
A: Hydro has set a new standard to better withstand strong winds/weather.
Q: Will the hydro be buried?
A: All relocations have been completed. High voltage lines remain but most of the lines are now buried.
General
Q: What is the website for accessing project information?
A: All information, photos, project updates and information can be found here, www.countyroad43expansion.com.
Q: What does the line around the project on the maps signify?
A: It is a property line but it does not specifically indicate that work is being done there.
Q: Will the community safety zone near the school remain in effect?
A: Yes. Safety is of the upmost importance during the duration of construction and all parties will work together to ensure the community safety zone will remain in effect over the next two and a half years.
Q: Where will the pedestrian crossing for the school be located?
A: Pedestrians will cross at the roundabout in front of Shoppers Drug Mart. This will be a controlled crossing.
Q: You mentioned a roundabout at Shoppers/St. Michael, but the entrances aren’t aligned. How will this work?
A: The entrance to the school will remain for now, including a left turn. The roundabout aligns with Shoppers and can be used by busses.
Q: Is the plan to connect the trails along the creek with a path under the bridge still intact?
A: Accommodations will be made now for future trail development, however the trail development itself is not within the scope of this project.
Q: Have snowmobiling trails and their access to services been considered?
A: This is being reviewed. Snowmobiling does not currently have designated accesses.
Q: With the intersection at 43 and 44 designed for two lanes on 44, do we anticipate future expansion of 44 north to four lanes? Additionally, how were decisions made regarding placement of median and turn lanes on County Road 43?
A: The roundabout at 43 and 44 will be designed to accommodate 4 lane expansion in other directions if needed in future. Regarding the second question, a median is the main intention, but we are keeping some turn lanes to start (mainly school access) and reviewing as we proceed.
Q: Is the project designed to accommodate the Mattamy subdivision development?
A: All development was taken into consideration, but that subdivision is outside of this project area.
Q: What is the timeline for fixing the on and off ramp at County Road 43 and Highway 116?
A: We have been advocating for ramp improvements for several years. The Ministry of Transportation did a full assessment 2 years ago and has just awarded a project tender in 2024. We expect ramp improvements to be completed in late September of 2024.
Q: How will McEwen’s corner be impacted by the roundabout widening?
A: The roundabout will come up to the curb at their parking lot but doesn’t touch their parking lot. The grass and ditches will be affected.
Q: What material is the centre median made of?
A: It will be a concrete apron with left turns cut through.